The start of construction of the first section of the Porto–Lisbon high-speed line was scheduled for this month, but following the rejection by the Portuguese Environment Agency (APA), the part of the execution project submitted by the AVAN Norte consortium will be delayed by at least three and a half months. On the second section, the delay already stands at nine ...








